04/07/2020

11:59 AM 2.00 hours (Task #818 (New): Time estimation on budbux)
Budbux meeting plus fixes minor issue plus Research in documentation for stripe integration Suraj Manandhar
11:32 AM 3.00 hours (Task #1308 (New): Bug Fixes mentioned by QA)
budbux discussion, fixes verification Sarina Byanjankar
11:26 AM 0.75 hour (Task #1040 (New): Budbux QA)
Discussion and confirmation on rebate expiry and task analytics show Rakesh Shrestha

04/06/2020

11:22 AM 1.50 hour (Task #1040 (New): Budbux QA)
budbux issue mentioned by client tested. Sarina Byanjankar

03/26/2020

04:52 AM 1.00 hour (Task #818 (New): Time estimation on budbux)
Meeting with budbux team about estimation for new change request. Suraj Manandhar

03/25/2020

11:56 AM 3.00 hours (Task #1040 (New): Budbux QA)
Feature change, new features reviews and discussion. And Team consultation on those features for Hr estimates. Rakesh Shrestha
11:37 AM 2.50 hours (Task #1040 (New): Budbux QA)
budbux client comment discussion and review new changed and replare estimation document Sarina Byanjankar
 